Construction Progress

Storage room and kitchen have been demolished

Construction fencing is in place.

Dirt is being hauled in and leveled to build up building pad.

The construction site entrance has been established

Footings for exterior walls have been poured.

Construction of exterior and interior concrete block wall have begun..

Underground utilities rough in and start corridor walls evident.

Plumbing pipes on site.

Electrical conduit stubbed up in block walls.

Looking west - underground utility rough in and stub up evident. Corridor walls taking shape.

Concrete blocks stored on site.

Progress of block work along east face of building.

Progress of block work along south face of building.

Door frame installation has started.

Plumbing stacks evident (foreground) at new restroom pods.

Progress at east corridor.

Block progress at the north face of the addition.

Brick sample panel has been laid up. Brick face and mortar need to be cleaned for inspection and proper comparison.

Close-up of sample panel.

Window rough opening with proper flashing at the window head.

Blocks properly racked back on the south auditorium wall.

View down corridor between east classrooms and auditorium.

Block progress at north auditorium wall.

Block progress at the east wall of the auditorium.

Rebar stored on site.

Block for south classroom walls stored in those areas.

Block progress at northeast classroom area.

Block and thru-wall flashing at south exterior wall face.

Mechanical equipment support frames stored on site.

Steel framing members stored on site.

East face of building with auditorium walls in the back.

South face of building.

Electrical wiring has been pulled to the junction boxes.

Wood nailers are being installed for base securement of the trusses.

Corridor between auditorium and kitchen.

North wall of auditorium.

Electrical panel boxes are installed in the large north storage room.

Mechanical closet blocked up with door frame in place.

Classroom wall in the southwest corner of the addition.

Scaffolding in the south corridor of the auditorium.

Masons are finishing up the block work for the interior partitions at the classrooms.

Plumbing stack and floor drain installed in the janitor's closet.

Plumbing chase between restrooms.

Pressure gauge installed on a water supply line.

Temporary lights have been installed.

The end wall framing for the high west gable is complete.

Typical level of finish in the classrooms.

De-watering and turning of the soil is starting to take place to prepare the dirt building pad for the gym foundation and slab.

Close- up of classroom addition overhang.

View of the east face of the addition. End wall/gable framing is complete and the ice and water shield is down.

The ice and water shield has been installed over the high and low roof decking.

Progress shot of the south face of the addition.

Progress shot of the north face of the addition.

Close-up of one of the vibration springs under the mechanical units.

Windows have been installed

The mechanicals closets are being framed

Double layers of sheet rocks are installed at the ceiling of the mechanical closets to achieve the required fire rating.

Copper lines for hot and cold water run in the janitor's closet to serve the three compartment sink.

Typical level of finish in the classrooms

The gable ends of the auditorium have been closed in with exterior grade gypsum sheathing.

Overview of site.