| Construction Progress |

Storage room and kitchen have been demolished
|

Construction fencing is in place.
|

Dirt is being hauled in and leveled to build up building pad.
|

The construction site entrance has been established
|

Footings for exterior walls have been poured.
|

Construction of exterior and interior concrete block wall have begun..
|

Underground utilities rough in and start corridor walls evident.
|

Plumbing pipes on site.
|

Electrical conduit stubbed up in block walls.
|

Looking west - underground utility rough in and stub up evident. Corridor walls taking shape.
|

Concrete blocks stored on site.
|

Progress of block work along east face of building.
|

Progress of block work along south face of building.
|

Door frame installation has started.
|

Plumbing stacks evident (foreground) at new restroom pods.
|

Progress at east corridor.
|

Block progress at the north face of the addition.
|

Brick sample panel has been laid up. Brick face and mortar need to be cleaned for inspection and proper comparison.
|

Close-up of sample panel.
|

Window rough opening with proper flashing at the window head.
|

Blocks properly racked back on the south auditorium wall.
|

View down corridor between east classrooms and auditorium.
|

Block progress at north auditorium wall.
|

Block progress at the east wall of the auditorium.
|

Rebar stored on site.
|

Block for south classroom walls stored in those areas.
|

Block progress at northeast classroom area.
|

Block and thru-wall flashing at south exterior wall face.
|

Mechanical equipment support frames stored on site.
|

Steel framing members stored on site.
|

East face of building with auditorium walls in the back.
|

South face of building.
|

Electrical wiring has been pulled to the junction boxes.
|

Wood nailers are being installed for base securement of the trusses.
|

Corridor between auditorium and kitchen.
|

North wall of auditorium.
|

Electrical panel boxes are installed in the large north storage room.
|

Mechanical closet blocked up with door frame in place.
|

Classroom wall in the southwest corner of the addition.
|

Scaffolding in the south corridor of the auditorium.
|

Masons are finishing up the block work for the interior partitions at the classrooms.
|

Plumbing stack and floor drain installed in the janitor's closet.
|

Plumbing chase between restrooms.
|

Pressure gauge installed on a water supply line.
|

Temporary lights have been installed.
|

The end wall framing for the high west gable is complete.
|

Typical level of finish in the classrooms.
|

De-watering and turning of the soil is starting to take place to prepare the dirt building pad for the gym foundation and slab.
|

Close- up of classroom addition overhang.
|

View of the east face of the addition. End wall/gable framing is complete and the ice and water shield is down.
|

The ice and water shield has been installed over the high and low roof decking.
|

Progress shot of the south face of the addition.
|

Progress shot of the north face of the addition.
|

Close-up of one of the vibration springs under the mechanical units.
|

Windows have been installed
|

The mechanicals closets are being framed
|

Double layers of sheet rocks are installed at the ceiling of the mechanical closets to achieve the required fire rating.
|

Copper lines for hot and cold water run in the janitor's closet to serve the three compartment sink.
|

Typical level of finish in the classrooms
|

The gable ends of the auditorium have been closed in with exterior grade gypsum sheathing.
|

Overview of site.
|
|
|